The last formal update on the Birnbeck Pier project, given on North Somerset Council’s website, was given in January 2025 and related to the tender process for the structural restoration work. The preliminary stabilisation works to the island buildings and cliff face, scheduled from Autumn to Winter 2024, are now completed. However, the next phase for the repair and renovation of the landside buildings does not appear to have been started, despite being scheduled for Spring 2025. The most recent update, shared mostly via social media, does not address the schedule for the project but rather explains why such a complex project takes so long and requires so much funding: more a rebuke to the mis-informed “nay-sayers” who proliferate social media. It is also notable that several of the Council’s planning applications for the project have not yet received planning approval, with three separate applications (each with their corresponding Listed Building Consent application) still pending consideration: 24/P/1907/FUL (pier deck reconstruction); 24/P/2010/FUL (lifeboat station) and 24/P/2439/R3 (island pavilion, boathouse café, “Pier View” internal alterations). In each, the last correspondence took place in January or February, and the statutory decision deadlines are now long passed. The applications should still be active and valid, however, and it might be that the Council have strategically delayed the issuing of the decisions such that they have more time to prepare for the works before the permissions expire after three years (just a speculation). Permission for the current building phase, for the avoidance of doubt, has already been granted and hopefully works will start imminently.